Borough of Shippensburg issued the following announcement on June 11
****UPDATE JUNE 11, 2020****
NEXT WEEK UPDATES!!!!!!! WEEK of JUNE 15th!
PLEASE NOTE THAT RONCA WILL BE PAVING (FINAL RESTORATION) STARTING MONDAY, JUNE 15TH. WORK WILL START AT THE CROSS AT KING/WAKLNUT BOTTOM HEADING WEST TO PRINCE STREET.
- Monday, June 15th PAVING CREW
- Saw cut starting at the cross intersection of King/Walnut Bottom – THERE WILL BE TRAFFIC PATTERN ADJUSTMENTS/ALTERNATING LANES, ETC!
- Monday, June 15th WATERLINE CREW
- Connect hydrants at King/Queen (SW corner)
- THERE WILL BE SINGLE LANE/ALTERNATING TRAFFIC LANES!!!!!
- Tuesday, June 16th PAVING CREW
- Start paving at the cross intersection of King/Walnut Bottom – THERE WILL BE TRAFFIC PATTERN ADJUSTMENTS/ALTERNATING SINGLE LANE!!!!!!!
- Tuesday, June 16th WATERLINE CREW
- Reconnect hydrant at S. Walters/King
- THERE WILL BE ALTERNATING/SINGLE LANE TRAFFIC!
- Wednesday, June 17th PAVING CREW
- Saw cutting/and or paving continues heading west – THERE WILL BE TRAFFIC PATTERN ADJUSTMENTS/ALTERNATING SINGLE LANE!!!!!!
- Wednesday, June 17th, 2020 WATERLINE CREW
- Reconnect services between Prince and Penn
- There may be times when traffic is reduced to single lane (south side reconnections)
- Thursday, June 18th, 2020 PAVING CREW
- Saw cutting/and/or paving continues heading west and ending at Prince –THERE WILL BE TRAFFIC PATTERN ADJUSTMENTS/ALTERNATING SINGLE LANE!!!!!!!
- Thursday, June 18th, 2020 WATERLINE CREW
- Reconnect services between Prince and Penn
- There may be times when traffic is reduced to single lane (south side reconnections)